Anima Hakuba

Construction Timeline

A structured development schedule for Anima Hakuba, from site preparation to completion.

Scheduled Completion

December 10, 2026

Project Overview

Project Name

Anima Hakuba

Location

Hakuba, Nagano, Japan

Project Type

Luxury Resort Villa Development

Site Excavation

February 2026

Construction Start

February 2026

Estimated Completion

December 10, 2026

Development Schedule

Each phase is carefully planned and executed to ensure the highest standards of quality, safety, and timely delivery.

  1. Feb2026

    1

    Site Preparation & Excavation

    The project begins with land preparation and excavation works to establish a solid foundation for construction.

    • Site clearing and preparation
    • Excavation and earthworks
    • Ground leveling
    • Initial infrastructure planning
    • Foundation area preparation
  2. Mar2026

    2

    Construction Commencement

    Full-scale construction begins, marking the official start of the building phase.

    • Foundation construction
    • Site logistics setup
    • Structural construction preparation
    • Contractor coordination
    • Construction safety management
  3. Apr–Jun2026

    3

    Structural Works

    The main building structure will be developed, with a focus on core structural execution.

    • Structural framework
    • Concrete and timber-related works
    • Roof structure preparation
    • Utility routing coordination
    • On-site quality control
  4. Jul–Sept2026

    4

    Exterior & Interior Construction

    Exterior finishing and interior construction progress, bringing the design to life.

    • Exterior facade works
    • Roofing and waterproofing
    • Windows and door installation
    • Interior wall and ceiling works
    • Mechanical, electrical, and plumbing coordination
  5. Oct–Nov2026

    5

    Final Finishing & Inspection

    Final finishing works, equipment installation, and inspections to ensure quality and completion readiness.

    • Interior finishes
    • Kitchen, bathroom, and equipment installation
    • Lighting and fixture installation
    • Final landscaping works
    • Safety and quality inspections
    • Pre-handover review
  6. Dec 102026

    6

    Scheduled Completion

    Anima Hakuba is scheduled for completion on December 10, 2026.

    • Final handover preparation
    • Operational readiness
    • Presentation for owners, partners, and stakeholders

From the Site

Latest Construction Photos

This gallery is updated regularly as construction progresses.

Follow the progress of Anima Hakuba

We are committed to transparency and will continue to share updates as construction progresses toward completion. For further enquiries, please contact us through official channels.